The company has also added a few feathers to its cap of success, as the following highly specialized projects illustrate  
   
 
Upgradation of the Road from Beeragonahalli near Yediyur (Km 0+000) to Mandya (Km 59+590) of SH-84 in the State of Karnataka on EPC Mode. 2023.19 million  
Upgradation of Road from Saundatti to Ramdurga (including Mullur ghat realignment) (Km 0+000 to Km 37+270) in link 21C and Ramdurga to Halgatti Junction, Ramdurga (Km 0+000 to 3+600) in link 21D in the State of Karnataka on EPC Mode. 1379.85 million to be completed in 24 Months and work is in progress.  
Construction of Roads & Storm Water Drains in Chinchbhuvan and Khapri areas in MIHAN at Nagpur, Maharashtra worth 390.55 million to be completed in 15 months and work is in progress.  
 
     
   
     
 
A. Highways , Runways
   
I
BOT (Annuity Projects)
   
1]
Development of 3 Roads under Ujjain Package on BOT (Annuity) Basis Package-IX, Under Madhya Pradesh Road Development Corporation Limited, Bhopal

Project worth 1642.20 million completed.
Client:- Madhya Pradesh Road Development Corporation Ltd, Bhopal
Duration- Scheduled 24 months, Actual 18 months.

   
2]
Development of Dariapur-Jasondi, Badwah-Katekut & Ashapur-Khalwa-Singot under Package III on BOT (Annuity) Basis, Under Madhya Pradesh Road Development Corporation Limited, Bhopal

Project worth 1238.30 million completed.
Client:- Madhya Pradesh Road Development Corporation Ltd, Bhopal
Duration- Scheduled 24 Months. Actual 21 months.

   
3]
Development of Dinara Datia (MDR) Road on BOT (Annuity)
Project worth 160.00 million completed.
Client :- Madhya Pradesh Road Development Corporation Ltd, Bhopal
Duration- Schedule 24 Months. Actual 24Months.
   
II
BOT (Toll + Annuity Projects)
   
4]
Development of Datia-Bhander (MDR) Road on BOT (Toll Plus Annuity) Basis Package-V, Under Madhya Pradesh Road Development Corporation Limited, Bhopal

Project worth 511.70 million completed.
Client:- Madhya Pradesh Road Development Corporation Ltd, Bhopal
Duration:- Scheduled 24 Months, Actual 22 months.

   
III
EPC Projects
5]
Construction of 4 Lane National Highway of Nagpur- Jabalpur (N.H.-7 )

NH Nagpur By-pass- 15.20 Km, work worth 1450.00 million- work Completed
Client- Oriental Structural Engineers Private Limited
Duration-Scheduled 24 months, Actual 24 months

   
6]
Resurfacing of Runway at AF Station Leh.

Project Worth 360.24 million Completed
Client- Military Engineering Services, Leh (Jammu & Kashmir)
Duration-Scheduled 24 months, Actual 18 months

   
7]
Improvement and Routine Maintenance of Nagpur - Hyderabad section of NH-7

Project Worth 187.78 millions. And 27.4 Km completed
Client- National Highway Authority of India
Duration-Scheduled 24 months, Actual 24 months

   
8]
Strengthening And Resurfacing of Taxi Tracks at AF Station Yelahanka (Banglore)

Project Worth 173.71 million completed
Client- Military Engineering Services, Bangalore (Karnataka)
Duration-Scheduled 4 months, Actual 4 months

   
9]
Airfield (Runway) Flexible & Rigid Pavement at AF Station Bidar

Project Worth 160.28 million completed
Client- Military Engineering Services,Bidar (Karnataka)
Duration-Scheduled 24 months, Actual 24 months

   
10]
Construction of Karanji Wani Ghuggus Chandrapur Road MSS-6 Section III - Km 61/300 to 81/395 in the state of Maharashtra.

Project Worth 223.60 million completed
Client- IVRCL, Pune
Duration - Scheduled 24 months, Actual 24 months

   
B. Aircraft Hangers
   
11]
Pre Engineered Building (PEB)-Aircraft Hanger at AF Station Bidar

Project Worth 213.11 million Completed-PEB of 50m x 113m of height 12.50m along with Apron & Taxi works of 55000 Sqm.
Client - Military Engineering Services, Bidar (Karnataka)
Duration-Scheduled 24 months, Actual 24 months

   
12]
Provision of Heavy Lift shed for Equipment at NSD Ghatkopar

Project Worth 128.78 million completed
Client - Military Engineering Services,Mumbai (Maharashtra)
Duration - Scheduled 18months, Actual 18 months

   
13]
Provision of Hanger including annexed with allied services at INS Hansa Goa

Project Worth 97.71 million completed
Client - Military Engineering Services, Panji (Goa)
Duration - Scheduled 12months, Actual 12 months

   
14]
Construction 22 feet high Protective wall for Project carnation at CAD Pulgaon

Project Worth 67.28 million completed
Client - Military Engineering Services
Duration - Scheduled 18months, Actual 18 months

   
C. Power Projects
   
15]
Civil works for railway siding and Marshalling Yard of 2 x 300 MW Coal Based group Captive Thermal Power Project

Project Worth 950.00 million completed
Client - Reliance Infrastructure Limited
Duration - Scheduled 10 months, Actual 24 months

   
D. Irrigation Projects
   
16]
Rehabilitation & Modernization of Pench Left Bank main canal from Km 0 to 16.00, Branches & Distributaries on it (Slice-II)

Project Worth 368.40 million completed
Client- Water Resources Department
Duration-Scheduled 42 months, Actual 51 months

   
17]
Rehabilitation & Modernization of Pench Left Bank main canal from Km 16.00 to 32.85, Branches & Distributaries on it (Slice-III)

Project Worth 310.18 million completed
Client- Water Resources Department
Duration-Scheduled 42 months, Actual 42 months

   
18]
Construction of Earth work and structure in KM 21 to KM 30 of Deoli Branch canal

Project Worth 220.00 million completed
Client- Lower Wardha Project Division
Duration-Scheduled 24 months, Actual 24 months

   
 
     
 
Home About us l  Services Clients Careers Feedback Contact us
   
 
Copyright © 2008 D.P. Jain & Co. Infrastructure Pvt. Ltd. All Rights Reserved.